公司新聞
對(duì)于醫(yī)藥化工設(shè)備安裝的整體質(zhì)量控制
信息來(lái)源: http://www.jnshhbkj.com 時(shí)間:2019-02-09 14:40:45
一.醫(yī)藥化工設(shè)備安裝預(yù)備期間的質(zhì)量操控
Quality control during the process of pharmaceutical chemical equipment installation
(1)檢查設(shè)備單位提交的設(shè)備設(shè)備施工組織規(guī)劃和設(shè)備施工計(jì)劃。
(1) check the equipment equipment construction organization plan and equipment construction plan submitted by the equipment unit.
(2)查看工作條件:如運(yùn)送路途、水、電、氣、照明及消防設(shè)施;首要材料、機(jī)具及勞動(dòng)力是不是執(zhí)行,土建施工是不是已滿意設(shè)備設(shè)備請(qǐng)求。設(shè)備工序中有恒溫、恒濕、防震、防塵、防輻射請(qǐng)求時(shí)是不是有相應(yīng)的保證辦法。當(dāng)氣象條件晦氣時(shí)是不是有相應(yīng)的辦法。
(2) check the working conditions such as transportation, water, electricity, gas, lighting and fire fighting facilities; primary materials, equipment and labor is not implemented, civil construction is not satisfied with the equipment and equipment requirements. Is there a corresponding guarantee method in the process of equipment with constant temperature, humidity, shock, dust and radiation protection. When weather conditions are bad when there is a corresponding approach.
(3)選用建筑結(jié)構(gòu)作為起吊、轉(zhuǎn)移設(shè)備的承力點(diǎn)時(shí)是不是對(duì)結(jié)構(gòu)的承載力進(jìn)行了核算,是不是征得規(guī)劃單位的贊同。
(3) bearing point selection of building structure as the lifting and transfer device is not on the bearing capacity of the structure of accounting, is not the consent of planning units agree.
(4)設(shè)備中選用的各種計(jì)量和查看用具、儀器、外表和設(shè)備是不是契合計(jì)量規(guī)則(精度等級(jí)不得低于被檢目標(biāo)的精度等級(jí))。
(4) the equipment used in the equipment and the measuring instruments, instruments, appearance and equipment are not in accordance with the rules of measurement (accuracy level shall not be lower than the accuracy of the target).
(5)查看設(shè)備單位的質(zhì)量管理體系是不是樹立及健全,督促其不斷完善。
(5) to see whether the quality management system of the equipment unit is set up and sound, and urge its continuous improvement.
二.醫(yī)藥化工設(shè)備安裝進(jìn)程的質(zhì)量操控
Two. Quality control of pharmaceutical chemical equipment installation process
醫(yī)藥化工設(shè)備安裝進(jìn)程的質(zhì)量操控首要包括:設(shè)備根底查驗(yàn)、設(shè)備就位、調(diào)平與找正、二次灌漿等不同工序的質(zhì)量操控。
Pharmaceutical chemical equipment installation process quality control mainly includes: equipment foundation inspection, equipment in place, leveling and looking for, two grouting and other different process quality control.
(一)設(shè)備設(shè)備進(jìn)程質(zhì)量操控關(guān)鍵:
(a) key to the quality control of equipment and process:
(1)設(shè)備進(jìn)程中的隱蔽工程,隱蔽前有必要進(jìn)行查看查驗(yàn),合格后方可進(jìn)入下道工序。
(1) the hidden works in the process of the equipment, it is necessary to conduct inspection and inspection before being hidden, and then go to the next working procedure.
(2)設(shè)備設(shè)備中要堅(jiān)持施工人員自檢,下道工序的互檢,設(shè)備單位專職質(zhì)檢人員的專檢及監(jiān)理工程師的復(fù)檢(和抽檢)并對(duì)每道工序進(jìn)行查看和記載。
(2) equipment and equipment to adhere to the construction of self inspection, the next process of mutual inspection, the equipment unit full-time quality inspection personnel and inspection of the supervision engineer (and sampling) and to view and record each process.
(3)設(shè)備進(jìn)程運(yùn)用的材料,如各種清洗劑、油脂、潤(rùn)滑劑、緊固件等有必要契合規(guī)劃和商品規(guī)范的規(guī)則,有出廠合格證實(shí)及設(shè)備單位自檢成果。
(3) the materials used in the process of the equipment, such as various cleaning agents, greases, lubricants, fasteners, etc., are necessary to comply with the rules of the planning and commodity specifications.
(二)設(shè)備基礎(chǔ)的質(zhì)量操控
(two) quality control of equipment foundation
設(shè)備就位前,設(shè)備單位應(yīng)對(duì)設(shè)備根底進(jìn)行查驗(yàn),在其自檢合格后提請(qǐng)監(jiān)理工程師進(jìn)行查看。通常是查看根底的外形幾許尺度、方位、混凝土強(qiáng)度等項(xiàng)。
Before the equipment is in place, the equipment unit shall inspect the equipment foundation, and then bring it to the supervision engineer for inspection. Usually look at the basic shape of several scales, bearings, concrete strength, etc..
監(jiān)理工程師對(duì)設(shè)備根底查看查驗(yàn)時(shí)還應(yīng)留意:
Supervision engineer should also pay attention to check the equipment foundation:
(1)地點(diǎn)根底外表的模板、地腳螺栓、固定架及顯露根底外的鋼筋等有必要撤除等。
(1) it is necessary to remove the template, the anchor bolt, the fixing frame and the exposed steel bar, etc..
(2)所有預(yù)埋件的數(shù)量和方位要準(zhǔn)確。
(2) the number and range of all anchors must be accurate.
(三)設(shè)備就位和調(diào)平找正
(three) locating and leveling of equipment
1.設(shè)備就位的質(zhì)量操控
1 quality control of equipment in place
監(jiān)理工程師的質(zhì)量操控,即是對(duì)設(shè)備單位的丈量成果進(jìn)行復(fù)核,并查看其丈量方位是不是契合請(qǐng)求。
The quality control of the supervision engineer, that is, the measurement results of the equipment unit for review, and to see whether the measurement of the position is not fit request.
2.設(shè)備調(diào)平找正的質(zhì)量操控
2 quality control of leveling equipment
設(shè)備調(diào)平找正分為設(shè)備找正、設(shè)備初平及設(shè)備精平三個(gè)進(jìn)程。醫(yī)藥化工設(shè)備安裝監(jiān)理工程師要對(duì)設(shè)備單位挑選的測(cè)點(diǎn)進(jìn)行查看及確認(rèn),對(duì)設(shè)備調(diào)平找正運(yùn)用東西、量具的精度進(jìn)行審閱,以保證精度滿意質(zhì)量請(qǐng)求。
Equipment leveling is divided into three parts, namely, the equipment is correct, the equipment is flat and the equipment is flat. Pharmaceutical and chemical equipment installation supervision engineer should check and confirm the measurement points selected by the equipment unit, and check the accuracy of the equipment and the measuring tools in order to ensure the accuracy and quality requirements.
(四)設(shè)備的復(fù)查與二次灌漿
(four) review of equipment and two grouting
(五)設(shè)備設(shè)備質(zhì)量記載材料的操控
(five) handling of equipment quality records
1.設(shè)備單位質(zhì)量管理查看材料
1 equipment quality management view material
2.設(shè)備根據(jù)
2 equipment according to
3.設(shè)備、材料的質(zhì)量證實(shí)
3 quality certification of equipment and materials
4.設(shè)備設(shè)備查驗(yàn)材料
4 equipment and materials
5.醫(yī)藥化工設(shè)備安裝監(jiān)理工程師對(duì)材料的請(qǐng)求
5 pharmaceutical chemical equipment installation supervision engineer for material requirements
(1)設(shè)備的質(zhì)量記載材料要實(shí)在、完全完整,簽字完備;
(1) the quality records of equipment shall be true, complete and complete;
(2)所有材料定論要明確;
(2) all materials should be clear;
(3)質(zhì)量記載材料要與設(shè)備進(jìn)程的各期間同步;
(3) the quality records should be synchronized with the process of the equipment;
(4)組卷、歸檔要契合建設(shè)單位及承受運(yùn)用單位的請(qǐng)求,世界出資的大型項(xiàng)目,材料應(yīng)契合世界重點(diǎn)工程對(duì)查驗(yàn)材料的請(qǐng)求。
(4) the composition of the test paper, the filing should be consistent with the requirements of the construction unit and the use of units, large projects funded by the world, the material should comply with the requirements of the world's key projects on the inspection of materials.
三、設(shè)備試運(yùn)轉(zhuǎn)的質(zhì)量操控
Three, the quality control of equipment commissioning
設(shè)備經(jīng)查驗(yàn)合格后,還有必要進(jìn)行試工作,這是保證設(shè)備配套投產(chǎn)正常工作的重要環(huán)節(jié)。
After the inspection of the equipment, it is necessary to carry out trial work, which is an important part of the equipment to ensure the normal operation.
(一)設(shè)備試運(yùn)轉(zhuǎn)條件的操控
(1) manipulation of equipment commissioning conditions
出產(chǎn)設(shè)備試運(yùn)轉(zhuǎn)條件有以下五點(diǎn):
Production equipment commissioning conditions have the following five points:
(1)設(shè)備及其隸屬設(shè)備、管路等悉數(shù)施工設(shè)備結(jié)束,施工記載機(jī)質(zhì)量操控材料完備,并經(jīng)監(jiān)理工程師查看契合請(qǐng)求:
(1) equipment and its subordinate equipment, pipelines and other construction equipment at the end of the construction record machine quality control material is complete, and the supervision engineer to see the fit request:
(2)需要的動(dòng)力等契合試運(yùn)轉(zhuǎn)的請(qǐng)求;
(2) the required power, such as the requirements of the trial operation;
(3)大型、雜亂、精密儀器,是運(yùn)轉(zhuǎn)計(jì)劃或操作規(guī)程已由設(shè)備單位編制完成,并經(jīng)總監(jiān)理工程師及建設(shè)單位檢查同意;
(3) large, disorderly, precision instruments, is the operation plan or operating procedures have been prepared by the equipment unit, and by the chief engineer and the construction unit to check the agreement;
(4)參加試運(yùn)轉(zhuǎn)的施工人員了解設(shè)備的結(jié)構(gòu)、功能、設(shè)備技能文件,把握操作規(guī)程及試運(yùn)轉(zhuǎn)操作,設(shè)備單位完成了有關(guān)的技能交底;
(4) to participate in the trial operation of the construction personnel to understand the structure of the equipment, functions, equipment, technical documents, grasp the operating procedures and commissioning operation, the equipment unit to complete the relevant skills;
(5)經(jīng)現(xiàn)場(chǎng)查看設(shè)備及周圍環(huán)境已打掃干凈,設(shè)備鄰近沒有粉塵或噪聲較大的工作。
(5) the equipment and the surrounding environment have been cleaned up, and the equipment has no dust or noise.